    Basement Finish Checklist

    A basement finish has fewer expensive finishes than a kitchen and far more decisions that get permanently buried in a wall. Where the TV goes, where the speakers go, where the data drops land — all of that is cheap to do before drywall and expensive to do after.

    Download the printable PDF

    We do not start until your materials are here

    Every finish material on this list has to be physically at your home before we begin. Not ordered. Not shipped. Not out for delivery. Delivered, and checked by us.

    We give you a completion timeframe and we hold to it. The only way we can do that is to control what is in the house on day one. A material that is still in transit has too many ways to fail — backorder, freight delay, shipping damage, wrong color, wrong quantity, wrong dye lot — and every one of those lands on your finish date instead of the supplier's.

    So if the materials are not here, we do not start. Your project does not become a slower job. It becomes a later start. That is exactly what protects the timeframe we promised you.

    Two exceptions: a bar countertop is cut after the cabinets are set, and if the basement includes a shower, the glass company measures after the tile is complete and brings you the style and finish options at that visit.

    The other thing to know up front is that drywall is the longest single phase of your project. Hanging, taping, three coats of mud, and sanding runs one to two weeks on its own, and there is no way to speed it up without the finish showing it.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • Anything marked "On site before we start" has to be at the house before day one. Anything marked "Before we start" is a decision we need from you by then, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 31 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    Layout and big decisions

    These have to be settled before we frame. After framing, changing them means tearing walls back out.

    Your signed approval on the layout — room sizes, door locations, closet placement

    Due by: Before we start

    Drywall or drop ceiling. Drywall looks better; a drop ceiling gives you access to everything above it. Pick one, and tell us where you want access panels

    Due by: Before we start

    Required by code for any bedroom. Confirm the location with us before we frame the wall

    Due by: Before we start

    Tread material, railing style and finish, and whether you want the stairs carpeted or finished

    Due by: On site before we start

    Model number and cutout dimensions for an electric or gas unit. We frame the opening around it

    Due by: On site before we start

    If you are adding one, every item on our Bathroom checklist applies here too. Ask us for that sheet

    Due by: Before we start

    Inside the walls

    Decide all of this before rough-in. After drywall, each one becomes a repair job instead of a wire pull.

    Where each TV goes, the screen size, and the mount type. We install blocking and run conduit so the cords stay hidden

    Due by: Before we start

    Where you want in-wall or in-ceiling speakers, and whether you want a rack location

    Due by: Before we start

    Which rooms need hardwired network, and where the equipment will live

    Due by: Before we start

    Any changes to existing systems, or new equipment you want us to plumb and power

    Due by: Before we start

    Extend the existing ductwork or add a mini-split. If it is a mini-split, we need the model number

    Due by: Before we start

    Whether you want a bar sink, and if so, roughly where. The drain often has to be cut into the slab

    Due by: Before we start

    Wet bar or kitchenette

    Same rule as a kitchen — we cannot produce the bar design rendering until we have a rough layout and the dimensions of anything going under the counter: beverage fridge, ice maker, dishwasher

    Due by: Before we start

    Style, finish and signed shop drawing. These have the same lead times as kitchen cabinets

    Due by: On site before we start

    Brand and color, or the reserved slab if it is natural stone

    Due by: Reserved before we start

    Model numbers and finish

    Due by: On site before we start

    Model numbers, cutout dimensions, water lines, and circuit requirements

    Due by: On site before we start

    Tile with 15% overage, trim pieces, and grout color

    Due by: On site before we start

    Flooring, doors and trim

    Material with 10% overage. In a basement, confirm it is rated for below-grade use

    Due by: On site before we start

    Whatever your flooring manufacturer requires — it affects the warranty

    Due by: On site before we start

    Matched to your flooring, one for every threshold

    Due by: On site before we start

    Style and whether solid core. Solid core is worth it on a media room or a bedroom

    Due by: On site before we start

    Finish and count, split between passage, privacy, and any locking doors

    Due by: On site before we start

    Profile and height. Matching the upstairs is usually the right call

    Due by: Before we start

    Wire, wood, or a closet system, and the configuration for each closet

    Due by: On site before we start

    Lighting and electrical

    Count, trim finish, and color temperature. Basements need more light than people expect

    Due by: On site before we start

    Model numbers and weight. Fans and heavy fixtures need blocking

    Due by: On site before we start

    White, almond, or black, plus the plate style

    Due by: Before we start

    Which circuits you want dimmed. A media area almost always wants dimmers

    Due by: Before we start

    Under-stair, toe-kick, tray ceiling, or bar lighting — all of it is wired at rough-in

    Due by: On site before we start

    Paint

    Brand, color name and number, and sheen for each surface

    Due by: Before we start

    Order these first, they decide when we can start

    • Where your TVs, speakers and data drops go. These cost almost nothing before drywall and hundreds of dollars after.
    • Bar cabinets, if you are including a bar. Generally two to four weeks like kitchen cabinets, and subject to change.
    • Flooring. Basements need a below-grade rated product, and the one you like may not be one.
    • Interior doors and trim. These are the last things installed and the most commonly forgotten until we are standing there ready to hang them.
    Part 2

    The order the work actually runs in

    A basement runs in a long, steady sequence with two stretches you should expect: waiting on inspections, and drywall.

    Inspections are the part of the schedule we least control. We schedule them the day the work is ready, and then we wait for the inspector’s calendar. On a basement there are usually four separate inspections.

    Every phase below assumes your materials were already at the house on day one. That assumption is what the whole schedule rests on.

    1. Design, permit application and selections

    Typical time: 2–5 weeks

    Final layout signed off, permit submitted, and every material on page 1 delivered to the house

    2. Permit review and issuance

    Typical time: 1–4 weeks

    Entirely on the jurisdiction’s clock, not ours

    3. Moisture and foundation prep

    Typical time: 1–5 days

    Any water issue has to be solved before we frame. A wet basement will ruin a finished one

    4. Framing

    Typical time: 3–7 days

    Final layout, fireplace model, recessed medicine cabinet or niche locations

    5. Rough electrical, plumbing, HVAC and low voltage

    Typical time: 4–8 days

    TV, speaker and data locations, bar and bath fixtures spec’d and on site

    6. Rough inspections

    Typical time: 3–7 days

    Building, electrical, plumbing and HVAC, often on separate visits

    7. Insulation

    Typical time: 1–3 days

    Nothing needed from you

    8. Insulation inspection

    Typical time: 1–3 days

    Another wait on the inspector

    9. Drywall: hang, tape, three coats, sand

    Typical time: 7–12 days

    The longest single phase. Each coat has to dry before the next one goes on

    10. Prime and paint

    Typical time: 3–5 days

    Colors and sheens selected

    11. Flooring

    Typical time: 2–4 days

    Flooring delivered and acclimated for the time the manufacturer requires

    12. Trim, doors and closet shelving

    Typical time: 3–5 days

    Doors, hardware, trim profile and shelving all on site

    13. Bar cabinets and countertop template

    Typical time: 2–3 days

    Cabinets delivered, sink on site for the template

    14. Bar countertop fabrication

    Typical time: 7–14 days

    Nothing happens on the bar during this stretch — we work elsewhere in the space

    15. Tile: bar backsplash and bath

    Typical time: 2–5 days

    All tile, trim and grout on site

    16. Finish electrical and plumbing

    Typical time: 2–4 days

    Every fixture on site and unboxed

    17. Paint touch-up and final clean

    Typical time: 1–2 days

    Nothing needed from you

    18. Final inspection, punch list and walkthrough

    Typical time: 1–3 days

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a basement finish

    1. Inspection scheduling. On a basement there are four or more inspections and each one is on the jurisdiction’s calendar. We build buffer in for this but it is the least predictable part of the job.
    2. Changing the layout after framing is up. It always looks different once the walls exist. If you want to move something, tell us the day the framing goes up — not the day the drywall goes on.
    3. Low-voltage decisions made too late. TV, speaker and network locations are free to change before rough-in and expensive to change after drywall.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    Bar cabinets

    Typical lead time: 2–4 weeks

    Order it by: As soon as the job is booked

    Below-grade rated flooring

    Typical lead time: 1–6 weeks

    Order it by: 3 weeks before the flooring phase

    Interior doors, prehung

    Typical lead time: 1–4 weeks

    Order it by: 3 weeks before the trim phase

    Egress window and well kit

    Typical lead time: 2–6 weeks

    Order it by: As soon as the job is booked

    Mini-split HVAC unit

    Typical lead time: 2–8 weeks

    Order it by: As soon as the job is booked

    Electric fireplace unit

    Typical lead time: 1–6 weeks

    Order it by: On site before we start

    Light fixtures and fans

    Typical lead time: 1–6 weeks

    Order it by: 3 weeks before rough-in

    Permit review

    Typical lead time: 1–4 weeks

    Order it by: Submit as early as possible

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a basement finish in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.

    Email
    Email Us
    Location
    Columbus, Ohio

    Business Hours

    Monday - Friday8:00 AM - 5:00 PM
    Saturday8:00 AM - 12:00 PM
    SundayClosed

    Request a Free Quote