    Kitchen Remodel Checklist

    A kitchen remodel is really two projects running at once: the work we do, and the products you buy. The second one is what usually decides how long the first one takes.

    Download the printable PDF

    We do not start until your materials are here

    Every finish material on this list has to be physically at your home before we begin. Not ordered. Not shipped. Not out for delivery. Delivered, and checked by us.

    We give you a completion timeframe and we hold to it. The only way we can do that is to control what is in the house on day one. A material that is still in transit has too many ways to fail — backorder, freight delay, shipping damage, wrong color, wrong quantity, wrong dye lot — and every one of those lands on your finish date instead of the supplier's.

    So if the materials are not here, we do not start. Your project does not become a slower job. It becomes a later start. That is exactly what protects the timeframe we promised you.

    Your countertop is the one exception. The slab is reserved at the yard before we start, but it cannot be cut until your cabinets are set and measured.

    Almost everything we build is sized around something you purchased. Cabinets are built around your appliances. Countertops are cut around your sink. Rough plumbing and electrical are placed around your range, your hood, and your pendant lights. If a spec arrives late, we are not just waiting on a box — we are waiting to find out where things go.

    One item in particular waits entirely on you. We cannot complete your cabinet design rendering until we have a rough layout of the kitchen and the dimensions of every appliance you plan to put in it. The rendering is what the cabinet order is built from, and the cabinet order is what sets your start date.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • Anything marked "On site before we start" has to be at the house before day one. Anything marked "Before we start" is a decision we need from you by then, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 32 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    Appliances

    Send these first. Cabinet sizes, gas lines, circuits, and venting are all built from these spec sheets.

    Model number, fuel type (gas / electric / induction), overall width, and the required gas line and circuit size from the spec sheet

    Due by: On site before we start

    Model numbers and the cutout dimensions listed on the spec sheet, plus circuit size

    Due by: On site before we start

    Model number, CFM rating, duct size and direction, and the mounting height you want above the range

    Due by: On site before we start

    Model number, width / depth / height including door swing, whether it needs a water line, and panel-ready yes or no

    Due by: On site before we start

    Model number and panel-ready yes or no

    Due by: On site before we start

    Model number, cutout dimensions, water line needs, and whether it requires a dedicated circuit

    Due by: On site before we start

    Model number, horsepower, and whether you want an air switch in the counter or a wall switch

    Due by: On site before we start

    Where we can keep the appliances once they arrive. All of them are here before we start, so we need a garage bay, a spare room, or somewhere dry and out of the work zone

    Due by: Arranged before we start

    Cabinetry and hardware

    Cabinets set your start date. Nothing after them can start early, so this section moves first.

    We cannot produce your cabinet design rendering without a rough layout of the room and the dimensions of every appliance going in it. The rendering is what the cabinet order is built from, so this is the first domino in the whole project

    Due by: Before we start

    Your signed approval on the final shop drawing and a physical color sample you have seen in your own light

    Due by: Before we start

    Pulls and knobs — count per the plan plus four spares, the finish, and the screw length if you have thick drawer fronts

    Due by: On site before we start

    Trash pull-out, spice rack, tray dividers, lazy susan, drawer inserts — these ship with the cabinet order

    Due by: On site before we start

    Material, length, bracket type and finish. We install blocking in the wall for these, so we need it before drywall

    Due by: On site before we start

    Countertops

    Countertops cannot be measured until the cabinets are set. That template date is the start of a fixed waiting period.

    Brand and color. For natural stone, the specific slab you walked and reserved at the yard, with the slab number

    Due by: Reserved before we start

    Picked from the fabricator’s samples

    Due by: At template

    How many holes and what goes in each one — main faucet, soap dispenser, filtered water, air switch

    Due by: At template

    Plumbing fixtures

    Model number, single or double bowl, undermount or farmhouse. A farmhouse sink changes the cabinet it sits in, so this has to be settled before the cabinets are ordered

    Due by: On site before we start

    Model number, finish, and pull-down or standard

    Due by: On site before we start

    Model number and finish. The valve goes in the wall at rough-in, so tell us early if you want one

    Due by: On site before we start

    Model number and whether the unit needs an outlet under the sink

    Due by: On site before we start

    Tile and flooring

    Tile delivered to the site with 15% overage. Include the trim or bullnose pieces, or tell us you want a metal edge profile instead

    Due by: On site before we start

    Chosen from our sample board held against your actual tile, not from a photo

    Due by: Before we start

    Material with 10–15% overage, plus the transition pieces to every adjoining room

    Due by: On site before we start

    Schluter or similar profile and finish, if you are using them

    Due by: On site before we start

    Lighting and electrical

    Every fixture location is set at rough-in, before the walls close. Changes after drywall mean opening the ceiling back up.

    Count, trim finish, and color temperature — 2700K reads warm, 3000K reads cleaner. Pick one and use it everywhere

    Due by: On site before we start

    Model number, how many, and the height you want them hanging above the counter

    Due by: On site before we start

    Tape or puck, dimmable or not, color temperature, and where the transformer can live

    Due by: On site before we start

    Model number and weight. Anything heavy needs blocking in the ceiling before drywall

    Due by: On site before we start

    White, almond, or black, plus the cover plate style

    Due by: Before we start

    Which circuits you want dimmed and whether you want smart switches

    Due by: Before we start

    Paint and finishes

    Brand, color name and number, and the sheen for each surface

    Due by: Before we start

    Ordered from your cabinet supplier with the cabinets so it matches the production run

    Due by: On site before we start

    Order these first, they decide when we can start

    • Appliance specs. Not the appliances themselves — just the spec sheets. We cannot even produce the cabinet design rendering without them, and the rendering is what the cabinet order is built from.
    • Cabinets. Generally two to four weeks depending on how much customization you want, though timing is always subject to change. This is the item that sets your start date.
    • The countertop slab. If you want natural stone, go to the yard and put your name on a specific slab before demo day, not after.
    • A custom or oversized hood. The framing above the range is built around it, so we need the model before we frame.
    Part 2

    The order the work actually runs in

    This is the order a kitchen runs in and roughly how long each phase takes. Your job may skip a phase or combine two of them, but the sequence rarely changes — each phase depends on the one before it.

    Read the last column closely. That is where your purchases land on the schedule.

    Every phase below assumes your materials were already at the house on day one. That assumption is what the whole schedule rests on.

    1. Design, selections and ordering

    Typical time: 2–6 weeks

    Rough layout and appliance dimensions to us, cabinet rendering approved, slab reserved, and every material on page 1 delivered to the house

    2. Permit, if the scope requires one

    Typical time: 1–3 weeks

    Plans submitted. Moving walls, gas, or plumbing usually triggers this

    3. Site protection and demolition

    Typical time: 1–3 days

    Your temporary kitchen set up somewhere else, and the room emptied

    4. Framing and structural changes

    Typical time: 1–4 days

    Final layout approved and any header or beam detail confirmed

    5. Rough plumbing, electrical and HVAC

    Typical time: 3–5 days

    All appliance specs, sink model, pot filler decision, pendant locations, under-cabinet lighting

    6. Rough inspections

    Typical time: 1–3 days

    Scheduled by us. Timing depends on the inspector’s calendar, not ours

    7. Insulation and drywall

    Typical time: 4–8 days

    Nothing needed from you

    8. Prime and first coat paint

    Typical time: 2–3 days

    Paint colors and sheens selected

    9. Flooring, if it runs under the cabinets

    Typical time: 1–3 days

    Flooring delivered, acclimated, and inspected

    10. Cabinet installation

    Typical time: 2–4 days

    Cabinets delivered and checked for damage before the crew starts

    11. Countertop template

    Typical time: 1–2 hours

    Sink and faucet physically on site — the fabricator measures around them

    12. Countertop fabrication

    Typical time: 7–14 days

    Nothing happens on site during this stretch. It is normal and it is already in the schedule

    13. Countertop installation

    Typical time: 1 day

    Access to the driveway and a clear path to the kitchen

    14. Backsplash tile

    Typical time: 2–3 days

    Tile, trim pieces and grout on site, dye lots checked

    15. Finish plumbing, electrical and appliance install

    Typical time: 2–3 days

    Every fixture and appliance on site and unboxed

    16. Trim, hardware and final paint

    Typical time: 2–3 days

    Cabinet hardware on site with spares

    17. Final inspection, punch list and walkthrough

    Typical time: 1–3 days

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a kitchen remodel

    1. Appliance specs arriving late. The cabinet order waits on them, and if they change after rough-in we are moving gas lines and circuits that were already run.
    2. The countertop slab not being selected and reserved. We cannot schedule the template, and the template is what starts the two-week fabrication clock.
    3. Tile arriving short or backordered. Tile crews are booked weeks out. If your tile is not here on their day, we lose the slot and wait for the next one.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    Cabinets, stock through custom

    Typical lead time: 2–4 weeks

    Order it by: As soon as the job is booked

    Standard appliances

    Typical lead time: 1–4 weeks

    Order it by: As soon as the job is booked

    Pro-style or panel-ready appliances

    Typical lead time: 6–16 weeks

    Order it by: Before we set a start date

    Custom or oversized range hood

    Typical lead time: Varies by model

    Order it by: As soon as the job is booked

    Countertop fabrication (after template)

    Typical lead time: 7–14 days

    Order it by: Cannot be rushed or started early

    Specialty or imported tile

    Typical lead time: 2–8 weeks

    Order it by: 4 weeks before the tile phase

    Light fixtures and pendants

    Typical lead time: 1–6 weeks

    Order it by: 3 weeks before drywall

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a kitchen remodel in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.

    Email
    Email Us
    Location
    Columbus, Ohio

    Business Hours

    Monday - Friday8:00 AM - 5:00 PM
    Saturday8:00 AM - 12:00 PM
    SundayClosed

    Request a Free Quote