    Home Addition Checklist

    An addition is the longest and most weather-dependent project we do, and it is the one where your purchasing decisions have the largest effect on the calendar. A kitchen can absorb a late decision. An addition usually cannot.

    Download the printable PDF

    Materials on site — how this works on an addition

    We do not build around materials that are still in transit. On a remodel that means everything is at the house before day one. An addition runs five or six months, though, and parking your interior finishes on an active site that long invites damage, weather and theft. So we stage it instead.

    1. 1Before we break ground. Every long-lead item ordered, with a written delivery date from the supplier in our hands.
    2. 2Before dry-in. Windows, exterior doors and roofing at the house. The building cannot be closed to the weather without them, and nothing inside starts until it is.
    3. 3After rough framing, before drywall. Every interior finish material at the house — flooring, trim, doors, lighting, fixtures, hardware.

    Miss the third deadline and we do not hang drywall. The job holds where it stands, and your completion date moves by however long the materials take. Staged is not the same as flexible.

    The only exceptions are made to fit after construction starts: the countertop slab, cut once your cabinets are set, and shower glass if the addition includes a bath — the glass company measures after the tile is complete and brings you the style and finish options at that visit.

    One item outranks everything else on this list: your windows and exterior doors. They run six to sixteen weeks, they cannot be installed until the framing is up, and nothing inside the addition can start until they are in and the building is closed to the weather. If your windows are late, every single phase after framing slides by exactly that much.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • The "Due by" column tells you which of the three deadlines above each item falls under. Anything marked "Before we start" is a decision we need from you, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 26 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    Approvals before anything starts

    None of this is construction. All of it can stop construction.

    Your submission to the HOA, sent as early as possible. Some boards meet monthly and take six to eight weeks to answer

    Due by: Immediately

    A current survey if your jurisdiction requires one or the addition is near a setback or easement

    Due by: Before permit application

    Signed and approved plans, with structural engineering where required

    Due by: Before permit application

    Only if the addition does not meet setback or lot coverage rules. This adds weeks — we will tell you early if it applies

    Due by: Before permit application

    Long-lead orders

    Order these the week the job is booked. They are the difference between a six-month addition and a nine-month one.

    Brand, line, color, grille pattern, and glass package. Six to sixteen weeks. This is the single item most likely to move your finish date

    Due by: On site before dry-in

    Brand, style, swing direction, color, and hardware finish. Same lead times as windows

    Due by: On site before dry-in

    Brand and color, matched as closely as possible to your existing roof

    Due by: On site before dry-in

    Product and color. If you have leftover material from the original build, give it to us — exact matches on older homes are often discontinued

    Due by: On site before siding

    Your confirmation of the roofline and pitch so we can order. Trusses are engineered to order

    Due by: Before framing

    Exterior finishes

    Color, and where you want the water to discharge

    Due by: On site before siding

    Colors, matched to the existing house

    Due by: On site before siding

    Model numbers and count for entry, soffit, and any flood lighting

    Due by: On site before drywall

    Style and finish, if the addition changes your entry

    Due by: On site before drywall

    If the addition ties into outdoor space, our Patio and Deck checklist applies too. Ask us for that sheet

    Due by: Before we start

    Mechanical and systems

    Extend the existing system, add a dedicated system, or use a mini-split. An addition often exceeds what the current furnace can carry

    Due by: Before we start

    If the addition includes a bathroom, your current water heater may need to be upsized

    Due by: Before we start

    An addition frequently triggers a panel upgrade or a subpanel. We will confirm this during design

    Due by: Before we start

    Interior finishes

    Material with 10% overage. Decide now whether you are matching the existing floor or transitioning to something new

    Due by: On site before drywall

    Style, solid or hollow core, plus hardware finish and count

    Due by: On site before drywall

    Baseboard and casing profile, matched to the existing house

    Due by: Before we start

    Brand, color name and number, and sheen for walls, ceilings and trim

    Due by: Before we start

    Model numbers, counts, and weights for anything that needs blocking

    Due by: On site before drywall

    White, almond, or black, plus plate style

    Due by: Before we start

    Configuration for each closet and any built-in cabinetry

    Due by: On site before drywall

    If the addition includes a kitchen or bathroom

    Every item on our Kitchen checklist applies, on the addition timeline: appliance specs before we break ground, the appliances and cabinets themselves at the house before drywall

    Due by: On site before drywall

    Every item on our Bathroom checklist applies. The shower valve and tub come earlier than the rest — they go in the wall at rough-in, which is before drywall

    Due by: On site before rough-in

    Order these first, they decide when we can start

    • Windows and exterior doors. Six to sixteen weeks, and the whole interior waits on them. Order them the week the job is booked.
    • HOA approval. It is free and it takes weeks. Submit it before you have even finalized your finishes.
    • Roof trusses. Engineered and built to order, and framing stops at the wall plates without them.
    • Siding or masonry that matches your existing house. Older products get discontinued, and finding a match takes time you do not want to spend in September.
    Part 2

    The order the work actually runs in

    An addition runs longest and has the most phases outside our control — permits, inspections, and weather. We build realistic buffer for all three, and we will tell you the moment one of them moves.

    The sequence below cannot be reordered. You cannot drywall a building that is not closed to the weather, and you cannot close it to the weather without your windows.

    Every phase below assumes you hit the three materials deadlines on page 1. They are what the schedule is built on.

    1. Design, engineering and HOA approval

    Typical time: 3–10 weeks

    Plans finalized, HOA submitted, survey obtained if required

    2. Permit review and issuance

    Typical time: 2–8 weeks

    On the jurisdiction’s clock. Nothing on site happens during this

    3. Utility locates and site preparation

    Typical time: 2–5 days

    Access to the yard, and anything you want protected moved out of the way

    4. Excavation

    Typical time: 1–4 days

    Dry enough ground to dig. Weather dependent

    5. Footings and footing inspection

    Typical time: 2–5 days

    Inspector availability

    6. Foundation walls, block or pour

    Typical time: 3–7 days

    Concrete needs cure time before we load it

    7. Waterproofing, drain tile and backfill

    Typical time: 2–4 days

    Nothing needed from you

    8. Framing: floor, walls and roof

    Typical time: 5–15 days

    Trusses delivered. This is the phase where it finally looks like a building

    9. Roof dry-in and shingles

    Typical time: 2–5 days

    Shingles on site, and two or three dry days

    10. Windows and exterior doors install

    Typical time: 1–3 days

    Windows and doors delivered and inspected. If they are late, everything after this waits

    11. Siding, brick or stone

    Typical time: 5–12 days

    On site before siding

    12. Rough plumbing, electrical and HVAC

    Typical time: 5–10 days

    All fixture and appliance specs, HVAC approach confirmed, panel capacity resolved

    13. Rough inspections

    Typical time: 3–7 days

    Multiple trades, often separate visits

    14. Insulation and insulation inspection

    Typical time: 2–5 days

    Inspector availability

    15. Drywall: hang, tape, three coats, sand

    Typical time: 7–14 days

    Nothing needed from you. It cannot be rushed without the finish showing it

    16. Prime and paint

    Typical time: 3–6 days

    Colors and sheens selected

    17. Flooring

    Typical time: 2–5 days

    On site before drywall

    18. Trim, doors and interior finish

    Typical time: 4–8 days

    Doors, hardware and trim on site

    19. Finish plumbing, electrical and fixtures

    Typical time: 3–5 days

    Every fixture and appliance on site

    20. Final grade, gutters and exterior touch-up

    Typical time: 2–4 days

    Gutter color confirmed, seed or sod decided

    21. Final inspections, punch list and walkthrough

    Typical time: 1–2 weeks

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a home addition

    1. Window and exterior door lead times. This is the number one cause of a late addition, and it is entirely decided in the first week of the project. Order at signing.
    2. Permit review. Two weeks in one jurisdiction and eight in another, for the same set of plans. We submit as early as we can and then we wait with you.
    3. Weather during excavation, foundation and framing. Wet ground cannot be dug, fresh concrete cannot be loaded, and an open roof cannot be left open. We work around it but we cannot work through it.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    Windows

    Typical lead time: 6–16 weeks

    Order it by: On site before dry-in

    Exterior and patio doors

    Typical lead time: 6–16 weeks

    Order it by: On site before dry-in

    Roof trusses

    Typical lead time: 3–8 weeks

    Order it by: As soon as the job is booked

    Siding or masonry, standard colors

    Typical lead time: 2–6 weeks

    Order it by: 4 weeks before the siding phase

    Siding or masonry, matching an older home

    Typical lead time: 4–12 weeks

    Order it by: As soon as the job is booked

    HVAC equipment

    Typical lead time: 2–10 weeks

    Order it by: As soon as the job is booked

    HOA architectural approval

    Typical lead time: 2–8 weeks

    Order it by: Before you finalize anything else

    Permit review

    Typical lead time: 2–8 weeks

    Order it by: As soon as plans are stamped

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a home addition in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.