    Patio and Deck Checklist

    Outdoor work is the one category where the biggest schedule factor is something nobody controls. We can work in cold and we can work in wind, but we cannot set pavers in standing water, we cannot pour concrete into mud, and polymeric sand needs a dry window to set. A week of rain is a week.

    Download the printable PDF

    We do not start until your materials are here

    Every finish material on this list has to be physically at your home before we begin. Not ordered. Not shipped. Not out for delivery. Delivered, and checked by us.

    We give you a completion timeframe and we hold to it. The only way we can do that is to control what is in the house on day one. A material that is still in transit has too many ways to fail — backorder, freight delay, shipping damage, wrong color, wrong quantity, wrong dye lot — and every one of those lands on your finish date instead of the supplier's.

    So if the materials are not here, we do not start. Your project does not become a slower job. It becomes a later start. That is exactly what protects the timeframe we promised you.

    There are no exceptions on an outdoor project. Every paver, board, rail and fixture is at the house before we dig.

    The second factor is approval. If you are in an HOA neighborhood, the architectural committee is often the longest single item on this list, and it costs nothing to start. Submit before you have picked a paver.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • Anything marked "On site before we start" has to be at the house before day one. Anything marked "Before we start" is a decision we need from you by then, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 27 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    Approvals first

    Free to start, and the thing most likely to hold up a spring project. Do this the week the job is booked.

    Your submission with a drawing and material selections. Two to eight weeks in many Columbus-area neighborhoods

    Due by: Immediately

    Needed if the work is near a setback, easement, or property line

    Due by: Before permit

    We call this in to OUPS. It takes 48 business hours and it is not optional

    Due by: Before excavation

    Required for decks over 30 inches above grade, roofed structures, and any gas or electric. We handle the filing

    Due by: Before construction

    Surface material

    Order all of it at once, from the same production lot. Two lots of the same paver are not the same color.

    Brand, style, color, and the laying pattern you want. Plus the border or soldier course, usually in a contrasting color

    Due by: On site before we start

    Broom, exposed aggregate, or stamped, plus the color and where you want the control joints

    Due by: Before we start

    Composite brand, line and color, or pressure-treated versus cedar. Composite decking commonly runs two to six weeks

    Due by: On site before we start

    Color, usually a contrast to the deck boards

    Due by: On site before we start

    Hidden fasteners or face screws. Hidden costs more and looks better

    Due by: On site before we start

    Sand color, matched to your paver

    Due by: On site before we start

    Railing, steps and structure

    Brand, style (cable, aluminum, composite, glass), color, and top rail material. Often a four to eight week lead

    Due by: On site before we start

    Style and whether you want them lit. Lit caps need wire run during framing

    Due by: On site before we start

    Material, matched or contrasted to the main surface

    Due by: On site before we start

    Style, color, and cap. Confirm the height — walls over four feet need engineering

    Due by: On site before we start

    Material, color, and whether it is freestanding or attached to the house

    Due by: On site before we start

    Features

    Kit model or a custom design, and gas or wood burning

    Due by: On site before we start

    Confirm whether you want gas to a grill or fire feature. It is a trench and a permit item, so it has to be decided before we build over the route

    Due by: Before we start

    Grill model with cutout dimensions, side burner, fridge, sink, and the countertop material

    Due by: On site before we start

    Model, mount type, and whether you want a weatherproof enclosure. Power and data run before the surface goes down

    Due by: On site before we start

    Model, dry weight, filled weight, and the electrical requirement — usually 50 amp at 240 volts. The pad has to be built for the filled weight

    Due by: On site before we start

    Lighting and electrical

    Count, style, and where the low-voltage transformer can be mounted

    Due by: On site before we start

    Model and count, if you are lighting the railing

    Due by: On site before we start

    How many and where. All exterior outlets need GFCI protection and in-use covers

    Due by: Before we start

    Whether the lights are switched from inside the house, outside, or on a timer

    Due by: Before we start

    Drainage and finishing

    Where you want roof water to go. Discharging it under a new patio is a lot easier than retrofitting it later

    Due by: Before we start

    Seed or sod for the disturbed areas around the work

    Due by: Before we start

    Whether you want the surface sealed, and matte or wet-look if so

    Due by: After install

    Order these first, they decide when we can start

    • HOA approval. It costs nothing and it can cost you two months. Submit the week the job is booked.
    • Composite decking and railing. Both commonly run two to eight weeks, and railing is often the longer of the two.
    • Pavers, ordered as one lot. A second order weeks later is frequently a visibly different color.
    • The gas line decision. Once we have built over that route, adding it later means taking part of your new patio back up.
    Part 2

    The order the work actually runs in

    Outdoor projects run in a sequence that depends heavily on weather and on cure times. Concrete footings need time before we load them, polymeric sand needs a dry window, and none of it can be compressed by adding people.

    The phase nobody sees is the one that decides whether the work lasts: base preparation and compaction. It is the least interesting part of the project and the reason your patio is still flat in ten years.

    Every phase below assumes your materials were already at the house on day one. That assumption is what the whole schedule rests on.

    1. Design, HOA approval and selections

    Typical time: 2–8 weeks

    HOA approved, and every material on page 1 delivered to the house

    2. Permit, where required

    Typical time: 1–4 weeks

    Decks over 30 inches, roofed structures, gas and electric

    3. Utility locate

    Typical time: 48 business hours

    Called in by us. It cannot be skipped or rushed

    4. Layout and excavation

    Typical time: 1–3 days

    Access to the yard and dry enough ground to dig

    5. Footings, piers and inspection

    Typical time: 2–5 days

    Concrete cure time before we build on it. Inspector availability

    6. Base preparation and compaction

    Typical time: 2–4 days

    The part nobody sees and the part that decides whether it stays flat

    7. Deck framing

    Typical time: 3–7 days

    Framing lumber and structural hardware on site

    8. Surface install: pavers, stone or decking

    Typical time: 3–10 days

    All surface material on site from a single production lot

    9. Steps and landings

    Typical time: 1–3 days

    Tread material on site

    10. Railing install

    Typical time: 1–3 days

    Railing delivered. This is frequently the item everyone is waiting on

    11. Walls, fire feature and outdoor kitchen

    Typical time: 2–8 days

    Block, kit, grill and appliances on site with cutout dimensions

    12. Electrical and lighting

    Typical time: 1–3 days

    Fixtures, transformer and outlet locations confirmed

    13. Polymeric sand, grout or sealer

    Typical time: 1–2 days

    A 24 to 48 hour dry window. We will not do this ahead of rain

    14. Final grade, seed or sod, and cleanup

    Typical time: 1–2 days

    Seed or sod decision made

    15. Final inspection and walkthrough

    Typical time: 1–2 days

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a patio or deck

    1. Weather. It is the biggest factor on any outdoor project and nobody controls it. Wet ground cannot be excavated or compacted, and polymeric sand needs a dry window on both sides of install.
    2. HOA approval. Boards that meet monthly can add six weeks to a project that takes three. Submit immediately, not after you have finalized selections.
    3. Composite decking and railing lead times. Railing in particular is often what keeps a finished-looking deck from being usable.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    Composite decking

    Typical lead time: 2–6 weeks

    Order it by: As soon as the job is booked

    Railing system

    Typical lead time: 4–8 weeks

    Order it by: As soon as the job is booked

    Pavers, in-stock styles

    Typical lead time: 1–2 weeks

    Order it by: 2 weeks before base prep

    Pavers, special order

    Typical lead time: 3–8 weeks

    Order it by: As soon as the job is booked

    Natural stone

    Typical lead time: 2–6 weeks

    Order it by: As soon as the job is booked

    Outdoor kitchen appliances

    Typical lead time: 2–10 weeks

    Order it by: As soon as the job is booked

    HOA architectural approval

    Typical lead time: 2–8 weeks

    Order it by: The week the job is booked

    Utility locate (OUPS)

    Typical lead time: 48 business hours

    Order it by: Before any digging

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a patio or deck in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.

    Email
    Email Us
    Location
    Columbus, Ohio

    Business Hours

    Monday - Friday8:00 AM - 5:00 PM
    Saturday8:00 AM - 12:00 PM
    SundayClosed

    Request a Free Quote