    Tile Installation Checklist

    Tile is the one trade where being slightly short on material is not a small problem. Tile is manufactured in batches, and two boxes from different production runs are usually a visibly different shade. If we run out mid-wall, the fix is often to take the wall back down and start over with a single lot.

    Download the printable PDF

    We do not start until your materials are here

    Every finish material on this list has to be physically at your home before we begin. Not ordered. Not shipped. Not out for delivery. Delivered, and checked by us.

    We give you a completion timeframe and we hold to it. The only way we can do that is to control what is in the house on day one. A material that is still in transit has too many ways to fail — backorder, freight delay, shipping damage, wrong color, wrong quantity, wrong dye lot — and every one of those lands on your finish date instead of the supplier's.

    So if the materials are not here, we do not start. Your project does not become a slower job. It becomes a later start. That is exactly what protects the timeframe we promised you.

    Your shower glass is the one exception, and there is nothing for you to do up front. Once the tile is complete the glass company comes out, measures, and brings you the style and hardware finish options to choose from right there. Figure another two to three weeks from that visit.

    So the most important thing on this list is quantity. Buy the full square footage plus the overage, in one order, and have it delivered to the site two days before we start so we can count it, inspect it for damage, and confirm every box is the same lot while it is still fixable.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • Anything marked "On site before we start" has to be at the house before day one. Anything marked "Before we start" is a decision we need from you by then, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 17 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    The tile itself

    All of it at the house and inspected by us before day one. We do not begin a tile job around a partial order.

    Full product name, size and finish, and the quantity: your square footage plus 15%. Make it 20% for herringbone, diagonal, or large-format tile

    Due by: On site before we start

    Confirm with the supplier that the entire order ships from one production run, and check the lot number on every box

    Due by: At purchase

    For niches, borders, or a feature wall, with overage

    Due by: On site before we start

    Bullnose, pencil, or chair rail. Many modern tiles have no matching bullnose — if you do not want a raw edge, pick a metal profile instead

    Due by: On site before we start

    Schluter or similar, plus the finish, if you are not using bullnose

    Due by: On site before we start

    Usually marble or a solid surface, sized to your opening

    Due by: On site before we start

    Grout and setting materials

    Chosen from our sample board held against your actual tile in the actual room. Grout color changes how a tile reads more than people expect

    Due by: Before we start

    Sanded, unsanded, or epoxy. Epoxy resists staining and is the right call in a heavy-use shower, but it costs more and installs slower

    Due by: Before we start

    Matched to the grout. Every change of plane gets caulk, not grout

    Due by: Before we start

    Required for natural stone, optional for porcelain. Confirm which you want

    Due by: After grout

    Layout decisions

    We will lay the room out and walk it with you before we set anything. Tell us now what matters most to you.

    Stack, running bond at a third or a half offset, herringbone, or diagonal. Pattern changes both the overage and the labor

    Due by: Before we start

    What you want prioritized — a full tile at the entry, centered in the niche, a symmetrical back wall. We cannot make all of them happen at once, so tell us the priority

    Due by: At layout

    How many, what size, and roughly what height

    Due by: Before we start

    Mat sized to the room and the thermostat model. It goes down under the tile

    Due by: On site before we start

    What comes after the tile

    Nothing to buy or pick up front. After the tile is finished the glass company measures and shows you the style and hardware finish options then, and it runs 10 to 21 days from there

    Due by: Chosen at the measure

    Model numbers and finish for every fixture, on site for finish day

    Due by: On site before we start

    Towel bars, hooks, shelves — so we can set blocking and place them before grout rather than drilling into finished tile

    Due by: On site before we start

    Order these first, they decide when we can start

    • The tile itself, with the full overage, in a single order and a single dye lot. This is the whole job.
    • Trim pieces or a metal edge profile. People consistently order beautiful field tile and forget how the edges get finished.
    • The heated floor mat, if you want one. It goes under the tile, so there is no adding it later.
    • Shower glass is the exception — nothing to order up front. It is measured after the tile is finished and adds two to three weeks at the end.
    Part 2

    The order the work actually runs in

    A tile installation is short, but it is unforgiving about order. The substrate has to be right before waterproofing, the waterproofing has to be proven before tile, and the tile has to cure before grout.

    Most failed tile jobs are not failed tile. They are failed substrates — a floor that flexes, a wall that is out of plane, or a shower pan that was never flood tested. We do not skip those steps, which is why the prep phase is longer than people expect.

    Every phase below assumes your materials were already at the house on day one. That assumption is what the whole schedule rests on.

    1. Selections, ordering and delivery

    Typical time: 1–6 weeks

    Whatever your tile’s lead time is. This is the whole front end of the job

    2. Tile received and inspected on site

    Typical time: Before day one

    We count it, check every box for the same dye lot, and check for damage. This happens before we start, while a problem is still fixable

    3. Protection and demolition

    Typical time: 1–2 days

    Room cleared. On older homes, expect to find something behind the old tile

    4. Substrate preparation

    Typical time: 1–3 days

    Subfloor repair, backer board, leveling, and a flatness check. The most important phase and the one you will never see

    5. Waterproofing and flood test

    Typical time: 1–2 days

    In a wet area we seal the assembly and hold water in it to prove it before any tile goes on

    6. Layout and dry-fit

    Typical time: A few hours

    Your sign-off on where the cuts land. Once we set the first tile, the layout is locked

    7. Setting the tile

    Typical time: 2–6 days

    All tile, trim and any heat mat on site

    8. Cure

    Typical time: 24 hours

    Thinset has to cure before grout. Nothing happens on site

    9. Grout, clean and seal

    Typical time: 1–2 days

    Grout color confirmed against the installed tile

    10. Caulk and final clean

    Typical time: Half a day

    Caulk color matched to grout

    11. Shower glass measure and order

    Typical time: 1 hour

    Only after grout is done and cured. The installer measures, shows you the options, and orders from there

    12. Shower glass fabrication

    Typical time: 10–21 days

    Nothing happens on site. The tile is finished and the shower is not yet usable

    13. Glass install, trim and accessories

    Typical time: 1 day

    Plumbing trim and accessories on site

    14. Walkthrough

    Typical time: 1 hour

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a tile installation

    1. Tile arriving short, damaged, or in mixed dye lots. This is the single most common tile problem and the reason we inspect the whole order two days early instead of on the morning we start.
    2. Substrate problems found at demolition. A flexing subfloor or a rotted wall has to be fixed before tile, and we will not set over it. We flag it the day we find it.
    3. Shower glass lead time. It cannot be measured until we are completely finished, and then it is two to three more weeks. The room will look done well before you can use it.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    In-stock porcelain or ceramic

    Typical lead time: 3–7 days

    Order it by: 2 weeks before start

    Special order tile

    Typical lead time: 2–6 weeks

    Order it by: As soon as the job is booked

    Imported or handmade tile

    Typical lead time: 4–12 weeks

    Order it by: Before we set a start date

    Natural stone slab or tile

    Typical lead time: 2–8 weeks

    Order it by: As soon as the job is booked

    Schluter or metal edge profiles

    Typical lead time: 1–3 weeks

    Order it by: With the tile order

    Heated floor mat and thermostat

    Typical lead time: 1–3 weeks

    Order it by: 2 weeks before start

    Custom shower glass (after tile)

    Typical lead time: 10–21 days

    Order it by: Cannot be ordered early

    Epoxy grout

    Typical lead time: 1–2 weeks

    Order it by: 2 weeks before start

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a tile installation in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.

    Email
    Email Us
    Location
    Columbus, Ohio

    Business Hours

    Monday - Friday8:00 AM - 5:00 PM
    Saturday8:00 AM - 12:00 PM
    SundayClosed

    Request a Free Quote