    Bathroom Remodel Checklist

    A bathroom is a small room with an unusual number of decisions buried inside the walls. Once the tile is on and the waterproofing is sealed, changing your mind is no longer a small change.

    Download the printable PDF

    We do not start until your materials are here

    Every finish material on this list has to be physically at your home before we begin. Not ordered. Not shipped. Not out for delivery. Delivered, and checked by us.

    We give you a completion timeframe and we hold to it. The only way we can do that is to control what is in the house on day one. A material that is still in transit has too many ways to fail — backorder, freight delay, shipping damage, wrong color, wrong quantity, wrong dye lot — and every one of those lands on your finish date instead of the supplier's.

    So if the materials are not here, we do not start. Your project does not become a slower job. It becomes a later start. That is exactly what protects the timeframe we promised you.

    Your shower glass is the one exception, and there is nothing for you to do up front. Once the tile is complete the glass company comes out, measures, and brings you the style and hardware finish options to choose from right there. Figure another two to three weeks from that visit.

    The single most important item on this list is the shower valve. The valve body is installed at rough-in, before any wall closes, and different manufacturers and different numbers of outlets need different valves. We cannot start rough plumbing without it in our hands.

    How to use this checklist

    • Tick the box once the item is bought and the spec sheet or model number is sent to us — not when you have decided on it. A decision we cannot see is not a decision we can build from.
    • Send specs to Tony.KVIConstruction@gmail.com. A photo of the model sticker or a link to the product page is enough.
    • Anything marked "On site before we start" has to be at the house before day one. Anything marked "Before we start" is a decision we need from you by then, not something you deliver.
    • If a line does not apply to your scope, cross it off with us at the pre-construction walkthrough so nothing is left looking unanswered.
    Part 1

    What you purchase, and when it is due

    0 of 27 checked

    Your ticks are saved in this browser only. Nothing is sent to us.

    Shower and tub

    Anything that goes inside a wall has to be purchased and on site before rough-in. There is no way around this.

    Brand, model and finish. The valve body goes in the wall at rough-in — rough plumbing cannot start without it

    Due by: On site before we start

    Model numbers and how many outlets you want running. The number of outlets decides which valve we install

    Due by: On site before we start

    Model number, exact dimensions, drain location (left or right), and alcove, drop-in, or freestanding

    Due by: On site before we start

    Model number and whether it is deck, wall, or floor mounted. A floor-mount filler has to be located before we close the floor

    Due by: On site before we start

    A decision, not a purchase — unless you want acrylic. Tell us whether you want a tile pan that we build and waterproof on site, or a preformed acrylic base. The tile pan is part of our work and there is nothing for you to buy. If you want acrylic, you buy that one and it has to be here with everything else

    Due by: Before we start

    How many, roughly what size, and what height. We frame and waterproof around these

    Due by: Before we start

    Nothing to buy or pick up front. After the tile is finished the glass company measures and shows you the style and hardware finish options then. Budget for it now and expect it at the very end

    Due by: Chosen at the measure

    Vanity, toilet and sinks

    Model or dimensions and finish. Confirm the door still clears it when it swings

    Due by: On site before we start

    Undermount, vessel, or integrated, and the faucet hole configuration — single hole or 8-inch spread

    Due by: On site before we start

    Model number and finish. Match the finish to everything else in the room

    Due by: On site before we start

    Model number and the rough-in dimension — 10, 12, or 14 inches, measured from the finished wall to the floor bolts

    Due by: On site before we start

    Model and size. A recessed medicine cabinet needs a cavity built into the wall, so we need it before framing

    Due by: On site before we start

    Tile and waterproofing

    All tile must be on site two days before the tile crew starts so it can acclimate and we can check the dye lots.

    Material with 15% overage. 20% if you want it run on a diagonal or in herringbone

    Due by: On site before we start

    Material with 15% overage, all from the same dye lot

    Due by: On site before we start

    Mosaic or feature tile with overage

    Due by: On site before we start

    Bullnose, pencil, or a Schluter-style metal profile and its finish. Many modern tiles have no matching bullnose — if you do not want a raw edge, pick a profile

    Due by: On site before we start

    Color from our board against your tile, and sanded, unsanded, or epoxy

    Due by: Before we start

    Usually marble or a solid surface. Confirm the material and where it transitions

    Due by: On site before we start

    Mat sized to the room and the thermostat model. It goes down under the tile, so it has to be here first

    Due by: On site before we start

    Lighting, fan and electrical

    Model number, CFM (a rough rule is 1 CFM per square foot, 50 minimum), and the sone rating if noise matters to you

    Due by: On site before we start

    Model, how many, and whether it mounts on the mirror or above it — that changes where we set the box

    Due by: On site before we start

    Trim finish and color temperature. Anything over the shower needs a wet-rated trim

    Due by: On site before we start

    White, almond, or black. GFCI outlets are required near water

    Due by: Before we start

    Model and power requirement. Both need a circuit run at rough-in

    Due by: On site before we start

    Accessories and paint

    How many, what finish, and roughly where you want them. We install blocking behind the drywall so they never pull out

    Due by: On site before we start

    Chosen at the glass measure, from what the installer brings. Have your faucet and fixture finishes on hand so the glass hardware matches the rest of the room

    Due by: Chosen at the measure

    Brand, color and number. Use a bathroom-rated paint — satin or semi-gloss

    Due by: Before we start

    Order these first, they decide when we can start

    • The shower valve and all shower outlets. This is the one item that can stop the job on day three. Buy it before demo.
    • Tile, with the full overage. Tile crews are scheduled tightly and a short order costs you their whole slot.
    • The toilet, specifically its rough-in dimension. A 10-inch rough-in toilet on a 12-inch drain means moving a drain line.
    • Shower glass is the exception to this list — there is nothing to order up front. Just know it is measured after the tile is done and adds two to three weeks at the end.
    Part 2

    The order the work actually runs in

    Bathrooms run in a tight, dependent sequence. Waterproofing has to pass before tile. The tile has to be finished before the glass can be measured and ordered. Nothing here can be run out of order.

    The most common surprise on a bathroom is the shower glass gap at the end. Your bathroom will look finished and still not be usable for two or three weeks while the glass is fabricated.

    Every phase below assumes your materials were already at the house on day one. That assumption is what the whole schedule rests on.

    1. Design and selections

    Typical time: 2–4 weeks

    Layout signed off, and every material on page 1 delivered to the house — valve, tub, tile, fixtures

    2. Permit, if the scope requires one

    Typical time: 1–2 weeks

    Moving fixtures or adding a bathroom usually triggers this

    3. Protection and demolition

    Typical time: 1–2 days

    Room cleared. Expect to find something behind the walls on an older home

    4. Framing, blocking and subfloor repair

    Typical time: 1–3 days

    Niche and bench sizes, accessory locations, recessed medicine cabinet

    5. Rough plumbing, electrical and venting

    Typical time: 2–4 days

    Shower valve, tub, tub filler type, fan, and any extra circuits — all physically on site

    6. Rough inspection

    Typical time: 1–3 days

    Scheduled by us, timed by the inspector

    7. Insulation, drywall and cement board

    Typical time: 2–4 days

    Nothing needed from you

    8. Waterproofing and flood test

    Typical time: 1–2 days

    We seal the wet area and hold water in the pan to prove it before any tile goes on

    9. Tile setting

    Typical time: 3–6 days

    All tile, trim, grout and heat mat on site, counted and dye-lot checked

    10. Grout, seal and cure

    Typical time: 1–2 days

    Grout color confirmed against the actual tile

    11. Paint

    Typical time: 1–2 days

    Color and sheen selected

    12. Vanity, toilet and finish plumbing

    Typical time: 1–2 days

    Vanity, top, faucets, toilet and trim all on site

    13. Shower glass measure and order

    Typical time: 1 hour

    Tile grouted and cured. The installer measures, walks you through style and finish options, and orders off those measurements

    14. Shower glass fabrication

    Typical time: 10–21 days

    Nothing happens on site. The room looks done and is not yet usable

    15. Glass install, accessories and hardware

    Typical time: 1 day

    Accessories and hardware on site

    16. Final inspection, punch list and walkthrough

    Typical time: 1–2 days

    You available to walk the job with us

    Shaded rows are stretches where little or nothing happens on site. They are part of the schedule, not a sign the job has stalled.

    The three most common delays on a bathroom remodel

    1. The shower valve not being on site. Rough plumbing is day three or four of a bathroom, and it simply cannot proceed without the valve in hand.
    2. Tile running short mid-install. A reorder is often a different dye lot, which means a visible line in your shower or starting the wall over.
    3. Shower glass lead time catching people by surprise. It cannot be ordered before your tile is finished, and it runs two to three weeks after that. Nothing compresses it.

    Typical lead times

    These are ranges we see in the Columbus market. Confirm the real number with your supplier when you buy, and tell us if it is longer than what is shown here.

    Shower valve and trim

    Typical lead time: 1–6 weeks

    Order it by: As soon as the job is booked

    Freestanding tub

    Typical lead time: 2–10 weeks

    Order it by: As soon as the job is booked

    Specialty or imported tile

    Typical lead time: 2–8 weeks

    Order it by: 4 weeks before the tile phase

    Stock vanity

    Typical lead time: 1–3 weeks

    Order it by: 3 weeks before finish plumbing

    Custom vanity

    Typical lead time: 6–12 weeks

    Order it by: As soon as the job is booked

    Custom shower glass (after tile)

    Typical lead time: 10–21 days

    Order it by: Cannot be ordered early

    Light fixtures

    Typical lead time: 1–6 weeks

    Order it by: 3 weeks before drywall

    Heated floor mat and thermostat

    Typical lead time: 1–3 weeks

    Order it by: 2 weeks before tile

    The other planning checklists

    Lead times and durations on this page are typical ranges for the central Ohio market and are not a quote. Your project is scheduled from your own scope, selections and supplier confirmations.

    Get a Free Estimate

    Planning a bathroom remodel in central Ohio? Send us your scope and we will walk the list with you before anything is ordered.

    Get In Touch

    Let's Build Something Great Together

    Ready to transform your home? Contact us today for a free consultation and estimate. We're here to answer your questions and bring your vision to life.

    Email
    Email Us
    Location
    Columbus, Ohio

    Business Hours

    Monday - Friday8:00 AM - 5:00 PM
    Saturday8:00 AM - 12:00 PM
    SundayClosed

    Request a Free Quote